Time and Cost Planning Using the Crashing Method in the Construction of the Nuclear Medicine Building of dr. Soedarso
DOI:
https://doi.org/10.53893/ijrvocas.v5i4.259Keywords:
Crashing Method, Time, Cost, HR, K3, Project CommunicationAbstract
The construction of the Nuclear Medicine Building of dr. Soedarso is a strategic effort to improve health services in West Kalimantan, especially in dealing with internal diseases such as cancer and heart. This project has an implementation deadline, so effective and efficient planning is required. This research aims to plan project time and costs using the crashing method, as well as consider aspects of human resources (HR), Occupational Health and Safety (K3), and project communication. The methodology used in the preparation of this final project is secondary data analysis in the form of RAB, AHSP, S curve, and basic price in 2024. The calculation of time and cost is carried out based on two approaches to project acceleration, namely the addition of working hours (overtime) and the addition of manpower. The analysis is complemented by the identification of the amount of labor needed, potential hazards at the work site, PPE needs, and communication used in the project. Normally for structural work, this project requires a cost of IDR 8.17 billion with a duration of 84 days. The results of this planning show that the crashing method with the alternative of adding working hours (overtime) costs IDR 8.19 billion, with a duration of 72 days (12 days faster than the normal duration). The crashing method with the alternative of adding labor costs 1DR 8.18 billion, with a duration of 67 days (17 days faster than the normal duration). Based on the results of these calculations, the crashing method can speed up project completion by considering labor productivity and cost-effectiveness. Recommendations from these results can be used as a consideration in making decisions on the implementation of project acceleration by contractors or other project implementing parties.
References
PMBOK. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide). 6th Editor. America: Project Management Institute.
Kerzner. (2013). Project Management: A Systems Approach to Planning, Scheduling, and Controlling (11th ed.). s.l.:Wiley.
Santoso. (2017). Project Acceleration Analysis Using the Crashing Method with the Addition of Four Hours of Working Hours and Work Shift System. Yogyakarta: Islamic University of Indonesia.
Elisabeth, R. A. (2017). Project acceleration analysis using the crashing method. e-Journal of Civil Engineering Matrix, p. 608.
Priyo, M. & Aulia, M. R. (2015). Application of the Time Cost Trade Off Method in Construction Projects (Case Study: Indonesian Building Construction Project). Scientific Journal of the Technical Universe Vol. 18 No. 1, pp. 30-43.
Suharto. (1997). Project Management. Second, editors. Jakarta: Erlangga.
Kerzner. (2017). Project Management: A Systems Approach to Planning, Scheduling, and Controlling (12th ed.). s.l.:Wiley.
Darsono, A. & Tanjung, M. (2017). SMK3 in Construction Projects. Jakarta: Salemba Teknika.
Additional Files
Published
How to Cite
Issue
Section
License
Copyright (c) 2026 Azza Arena, Nurul Fitriani, Raihanny Syafrina Fajry, Septian Eka Putra

This work is licensed under a Creative Commons Attribution 4.0 International License.
All articles published in International Journal of Research in Vocational Studies (IJRVOCAS) are distributed under the Creative Commons Attribution 4.0 International License (CC BY 4.0).
Under this license, users are permitted to share, copy, redistribute, adapt, transform, and build upon the published work for any purpose, including commercial use, provided that appropriate credit is given to the original authors and IJRVOCAS, a link to the license is provided, and any changes made are indicated.
Authors retain the copyright of their published articles and grant IJRVOCAS the right of first publication. The journal makes published articles freely and permanently available online immediately upon publication.
Proper attribution should include the author names, article title, journal title, publication year, volume, issue, page numbers or article number where applicable, DOI or URL, and a reference to the CC BY 4.0 license.
The full terms of the Creative Commons Attribution 4.0 International License are available at:
https://creativecommons.org/licenses/by/4.0/
By submitting a manuscript to IJRVOCAS, authors agree that accepted articles will be published under the CC BY 4.0 license.